The cooling towers of the former Brayton Point Station, the last coal-fired power plant in Massachusetts, was reduced to rubble in about 10 seconds when the controlled demolition started at 8 a.m ...
A cooling tower at the former BL England Power Station ... Hundreds of locals lined up — on land and on their boats — to watch the demolition which happened at 9:30 a.m. Within less than ...
For a split-second after the demolition plunger went down, the mighty cooling towers at St. Johns River Power Park stood as if they would remain for another 30 years as Jacksonville landmarks.
"Originally there was no question that we would announce the date of the demolition and enable interested citizens of the region to watch the case of the cooling towers," said Jörg Michels ...
A decades-old cooling tower at a shuttered Cape May County plant ... The group, which has hired an “internationally-recognized” demolition company said that “great care and preparation ...
JEA and Florida Power & Light contracted Total Wrecking & Environmental to handle the implosion of the cooling towers and demolition of the power park for $14.5 million. The project is expected ...
Mike Dammer, Lakeland Electric's engineer and demolition project lead, said the cooling towers for Units 2 and 3 are among the first large-scale buildings to be torn down in the year-and-a-half ...
That's it for our coverage of the Ironbridge cooling towers demolition. We hope you enjoyed it. A reminder that you can still share your memories and photos on the BBC Shropshire Facebook page ...
Controlled Demolition was hired by Beelsey’s for ... Ahead of the implosion, the interior “packing” of the cooling tower was already removed and transported to the Cape May Landfill.